| I. | Monitoring Schedule Frequency |
| A. | Periodic Inspection |
| B. | Compile and review (submit) data |
| II. | Peridic Inspection |
| A. | Field Conditions |
| | 1. | Walk the field and record any visible wet spots from the drip system. |
| | 2. | O.K.___ Repair___ Comments and remedial action ______________________________ |
| B. | Controller |
| | 1. | Lights and manual switch positions. |
| | | a. | Open the control panel and open the lid to the hydraulic unit and pump tank. Make sure all manual switches are in the automatic position. With Microprocessor on, verify power light and run light are on. |
| | | b. | O.K.___ Comments and remedial action ______________________________ |
| | 2. | Microprocessor input: See table in owners manual. |
| | | a. | O.K.___ Comments and remedial action ______________________________ |
| | 3. | Microprocessor output: Verify there is output only when in automatic operation. You may start automatic cycle with "Reset/Stop" button. |
| | | a. | O.K.___ Comments and remedial action ______________________________ |
| C. | Pump Tank Liquid Level Float Switches |
| | 1. | Check liquid level in the pump tank to confirm switch operation. |
| | | a. | If a float is down, its light should be off. Note; High level alarm float requires optional relay installed in control. |
| | 2. | O.K.___ Comments and remedial action ______________________________ |
| D. | Pump and Valve Operation |
| | 1. | Place pump "Hand-Off-Auto" switch in the "Hand" position to dead head pump against valves. Then open (optional) master valve. Flow meter should not turn indicating there are no leaks. |
| | 2. | O.K.___ Comments and remedial action ______________________________ |
| | 3. | With the pump running, place each zone valve in the "Hand" (open) position one at a time to check operation. With one zone valve open, flow should register on the flow meter. When the zone valve closes (off position), the flow should stop. |
| | 4. | O.K.___ Comments and remedial action ______________________________ |
| | 5. | With one zone valve open and flowing, close and reopen (optional) master valve to check operation. |
| | 6. | O.K.___ Comments and remedial action ______________________________ |
| | 7. | With the pump in the "Hand" position open the filter backwash valve for filter on and two for ten seconds then close. There should be no flow registering in the flow meter and you should hear the valves open and close. The backwash return valve diaphragm will rise then lower during backflush. |
| | 8. | O.K.___ Comments and remedial action ______________________________ |
| | 9. | Return all switches to the automatic position |
| E. | Hydraulic Unit |
| | 1. | Examine one filter and clean all filters as needed. |
| | 2. | Examine all hydraulic components for leaks, tubing crimps and other problems. |
| | 3. | Determine how many zones are in operation and the installed flow rates from the installation records. |
| III. | Annual Inspections (Includes Periodic Inspection) |
| A. | Extended Check - Zone Dose Rates |
| | 1. | Open the air release valve boxes and inspect. Make sure they close during the dose with no water leak after air is evacuated. |
| | 2. | O.K.___ Comments and remedial action ______________________________ |
| | 3. | Determine how many zones are in operation and the installed flow rates from the installation records.
|
| | 4. | O.K.___ Comments and remedial action ______________________________ |
| | 5. | With the pump in the "Hand" position, select the first zone by placing the zone valve switch in the "Hand" position. After pressurization time, check flow rates by reading the flow meter for a timed minute. Repeat for all zones. If flow varies by more than 10% from original flow rates, reset flow rates. |
| | 6. | O.K.___ Comments and remedial action ______________________________ |
| | 7. | After the final zone is checked, place the "Zone Return" valve in the "Hand" position while the "Zone Valve is still in the "Hand" position and verify that the flow rate increased to provide field flushing. |
| | 8. | O.K.___ Comments and remedial action ______________________________ |
| | 9. | Return appropriate switches to the automatic position. |
| | 10. | O.K.___ Comments and remedial action ______________________________ |
| | 11. | Press reset button for 5 seconds and check automatic zone dosing time. |
| | 12. | O.K.___ Comments and remedial action ______________________________ |
| B. | Tanks & Pumps |
| | 1. | Examine and clean effluent screens, filters, and floats as needed. |
| | 2. | O.K.___ Comments and remedial action ______________________________ |
| C. | Measure solids level in all tanks |
| | 1. | Septic Tank Tank Depth _______ Sludge Depth _______ |
| | 2. | Settling Tank Tank Depth _______ Sludge Depth _______ |
| | 3. | Dose Tank Tank Depth _______ Sludge Depth _______ |
| | | a. | Sludge pumping required? Yes___ No___ |
| IV. | Reporting |
| A. | Provide summary report to customer showing gallon flow to each field along with pertinent operating information and suggestions. |
| B. | Provide signed and dated inspection report to customer file and regulatory agency as needed. |
| C. | Have records available and be prepared to discuss operation and maintenance specifics with customer personnel. |
| V. | Operator Signature ___________________________________ Date: __________ |
| American Perc-Rite® Drip Startup Log | USER LOG |
| Line | As-Built | Description            Number of Zones: __ | Date | Date | Date | Date |
| 1 |   | BEDROOMS |   |   |   |   |
| 2 |   | GALLONS PER DAY |   |   |   |   |
| 3 |   | TEXTURE GROUP |   |   |   |   |
| 4 |   | GPD/FT2 DESIGN SOIL LOADING RATE |   |   |   |   |
| 5 |   | TOTAL LINEAR FEET TUBING |   |   |   |   |
| 6 |   | GPD/LF FT DESIGN TUBING LOADING |   |   |   |   |
| 7 |   | METER READING |   |   |   |   |
| 8 |   | ZONE 1 LINEAR FEET OF TUBING |   |   |   |   |
| 9 |   | ZONE 1 NUMBER OF FIELD FLUSH |   |   |   |   |
| 10 |   | ZONE 1 GPM DOSING FLOW RATE |   |   |   |   |
| 11 |   | ZONE 1 GPM TOTAL FLUSHING FLOW |   |   |   |   |
| 12 |   | ZONE 1 RUN TIME |   |   |   |   |
| 13 |   | ZONE 2 LINEAR FEET OF TUBING |   |   |   |   |
| 14 |   | ZONE 2 NUMBER OF FIELD FLUSH |   |   |   |   |
| 15 |   | ZONE 2 GPM DOSING FLOW RATE |   |   |   |   |
| 16 |   | ZONE 2 GPM TOTAL FLUSHING FLOW |   |   |   |   |
| 17 |   | ZONE 2 RUN TIME |   |   |   |   |
| 18 |   | ZONE 3 LINEAR FEET OF TUBING |   |   |   |   |
| 19 |   | ZONE 3 NUMBER OF FIELD FLUSH |   |   |   |   |
| 20 |   | ZONE 3 GPM DOSING FLOW RATE |   |   |   |   |
| 21 |   | ZONE 3 GPM TOTAL FLUSHING FLOW |   |   |   |   |
| 22 |   | ZONE 4 LINEAR FEET OF TUBING |   |   |   |   |
| 23 |   | ZONE 4 LINEAR FEET OF TUBING |   |   |   |   |
| 24 |   | ZONE 4 NUMBER OF FIELD FLUSH |   |   |   |   |
| 25 |   | ZONE 4 GPM DOSING FLOW RATE |   |   |   |   |
| 26 |   | ZONE 4 GPM TOTAL FLUSHING FLOW |   |   |   |   |
| 27 |   | ZONE 4 RUN TIME |   |   |   |   |
| 28 |   | PEAK ENABLE CYCLE COUNTER |   |   |   |   |
| 29 |   | HIGH LEVEL CYCLE COUNTER |   |   |   |   |
| 30 | CONTRACTOR STARTUP REPRESENTATIVE: |   |   |   |   |
| 31 | STARTUP DATE: |   |   |   |   |